Rt 12 Project Timeline (per MassHwy)
For anyone that is interested this is the basic timeline for the project.
- Sept 06 - Complete eminent domain takings and put project out to bid
- Dec 06 - Bid Openings (my note) probably followed by awarding contract(s)
- Spring 07 - begin constructions - the road will remain open through out constructions as one lane in each direction.
- Fall 08 - project completion